Schematic Design Rendering 3.2.2
SD 3.2.2 – 360° Panorama
SD 3.2.2 – 3D MODEL
OVERVIEW
Primary Style | Victorian |
Stories: | 2 |
Bedrooms: | 3 |
Baths: | 3 |
Garage Bays: | 3 |
Living Area: | 2,724 sq.ft. |
Foundation: | Basement |
Width: | 71′ |
Depth: | 54′ |
Styles: | Queen Anne Country Farmhouse |
FEATURES
Basement Ceiling Height | 7′ – 8″ |
Main Level Ceiling Height | 9′ |
2nd Level Ceiling Height | 8′ |
Exterior Wall Types: | 2x6 |
Front Facade: | Siding/ Stone |
Rear Facade: | Siding |
Left Side Facade: | Siding |
Right Side Facade: | Siding |
Wraparound Porch | Yes |
Vaulted/Cathedral Ceilings | Yes |
Kitchen Island | Yes |
Storage/Attic Space | Yes |
FirePlace | Yes |
1st Floor Master Suite | Yes |
Breakfast Nook | Yes |
Built-In Cabinets, Shelves, Desks | Yes |
French Doors | Yes |
Bay/Box/Bow Windows | Yes |
DETAILS
Total Finished Area | 2,724 sq. ft. |
Main Level Area | 1728 sq ft. |
2nd Level Area | 996 sq ft. |
Bonus Area | 0 sq ft. |
Unfinished Basement Area | 1,485 sq ft. |
Temporary Living Area | sq ft. |
Main Garage Area | 730 sq ft. |
Basement Garage Area | 1038 sq ft |
Deck Area | 645 sq ft. |
Total Construction Area | 6,622 sp ft. |
Max Ridge Height | 25 Ft |
Primary Roof Pitch Roof Framing |
12:12 Pitch Reuss/ Hand Framed |
ROOM SCHEDULE
SD 3.2.2 COST OF WORK ESTIMATES
Quality Level
|
Cost Range | |||
⇧ Average | Mid | |||
2 | 3 | 4 | ||
Percentage | Price | $/ Sq Ft | ||
TOTAL: | 100.00% | $478,362 | $175.61 | |
SITEWORK AND EXCAVATION | 2.72% | $12,995 | $4.77 | |
Site Clearing and Grading | 0.00% | $0 | $0.00 | |
Driveway, Walkway, Patio, Deck, Landscaping | 1.91% | $9,152 | $3.36 | |
Site Electrical, Gas, Water, Sewer Utility Extensions | 0.46% | $2,207 | $0.81 | |
Excavation (foundations) | 0.34% | $1,637 | $0.60 | |
FOUNDATIONS AND FOOTINGS | 9.99% | $47,789 | $17.54 | |
Home Foundation Walls | 0.67% | $3,208 | $1.18 | |
Home Footings | 0.38% | $1,797 | $0.66 | |
Deck Footings | 0.83% | $3,981 | $1.46 | |
Structural Concrete | 0.15% | $696 | $0.26 | |
Slabs (home, garage, basement, crawlspace) | 2.21% | $10,568 | $3.88 | |
Basement Excavation, Poured Concrete Walls/Footings, Drainage, Rigid Insulation | 5.76% | $27,540 | $10.11 | |
STRUCTURAL AND FRAMING | 21.83% | $104,423 | $38.33 | |
Home Floor Framing | 5.97% | $28,567 | $10.49 | |
Deck Floor Structure | 0.27% | $1,282 | $0.47 | |
Home Roof Structure | 5.35% | $25,587 | $9.39 | |
Deck Roof Structure | 1.06% | $5,077 | $1.86 | |
Garage Roof Structure and Shingles | 1.12% | $5,364 | $1.97 | |
Exterior Wall Framing, Insulation, Sheathing; House Wrap | 6.82% | $32,635 | $11.98 | |
Interior Partition Wall Framing | 1.24% | $5,909 | $2.17 | |
SIDING AND EXTERIOR TRIM | 6.21% | $29,713 | $10.91 | |
Exterior Wall Finish Material | 6.21% | $29,713 | $10.91 | |
Special Trim Complexity | 0.00% | $0 | $0.00 | |
EXTERIOR DOORS AND WINDOWS | 5.57% | $26,649 | $9.78 | |
Exterior Windows, Trim | 4.51% | $21,582 | $7.92 | |
Exterior Passage Doors, Doorwall, Overhead Garage Doors, Trim | 1.06% | $5,067 | $1.86 | |
ROOFING AND GUTTERS | 5.69% | $27,219 | $9.99 | |
Home Roofing Shingles | 2.20% | $10,534 | $3.87 | |
Porch Roofing Shingles | 0.22% | $1,040 | $0.38 | |
Roof Guttering | 0.62% | $2,944 | $1.08 | |
Special Roof Valley | 0.00% | $0 | $0.00 | |
Roofing Soffit and Fascia | 1.98% | $9,468 | $3.48 | |
Attic Insulation | 0.68% | $3,233 | $1.19 | |
CABINETRY AND COUNTERTOPS | 5.26% | $25,153 | $9.23 | |
Kitchen Cabinetry, Countertops, Flooring | 2.78% | $13,311 | $4.89 | |
Master Bathroom Cabinetry, Mirror, Countertops, Flooring | 1.50% | $7,157 | $2.63 | |
Full Bathroom Cabinetry, Mirror, Countertops, Flooring | 0.86% | $4,132 | $1.52 | |
Half Bath Cabinetry, Mirror, Countertops, Flooring | 0.12% | $552 | $0.20 | |
STAIRS AND RAILS | 1.60% | $7,665 | $2.81 | |
Stair Construction | 0.98% | $4,710 | $1.73 | |
Railing and Balusters | 0.62% | $2,954 | $1.08 | |
INTERIOR DOORS AND MILLWORK | 3.25% | $15,542 | $5.71 | |
Interior Doors, Hardware, Trim and Finishing | 2.41% | $11,533 | $4.23 | |
Baseboard Molding and Finishing | 0.84% | $4,009 | $1.47 | |
INTERIOR CEILING AND WALL COVERINGS | 6.87% | $32,847 | $12.06 | |
Interior Drywall: Walls | 1.73% | $8,273 | $3.04 | |
Interior Wall Primer and Painted Finish | 1.31% | $6,285 | $2.31 | |
Interior Drywall: Ceiling | 3.37% | $16,129 | $5.92 | |
Porch Ceiling Surfaces | 0.45% | $2,161 | $0.79 | |
INTERIOR CEILING AND WALL FINISHES | 4.15% | $19,845 | $7.29 | |
Interior Ceiling Primer and Painted Finish | 0.59% | $2,804 | $1.03 | |
Interior Floor Finishes | 3.56% | $17,041 | $6.26 | |
PLUMBING | 4.92% | $23,524 | $8.64 | |
Water Supply, Distribution, Waste, Water Heater | 1.74% | $8,327 | $3.06 | |
Bathroom Fixtures (Master Bath): Sink/Faucet, Toilet, Tub/Shower, Supply/Waste/Vent | 1.13% | $5,389 | $1.98 | |
Bathroom Fixtures (Full Bath): Sink, Faucet, Toilet, Tub/Shower, Supply, Waste, Vent | 0.77% | $3,676 | $1.35 | |
Bathroom Fixtures (Half Baths): Pedestal Sink, Faucet, Supply, Waste, Vent | 0.21% | $999 | $0.37 | |
Bathroom Fixtures (Half Baths): Toilet, Supply, Waste, Vent | 0.21% | $990 | $0.36 | |
Tub Enclosures | 0.17% | $800 | $0.29 | |
Kitchen Sink, Faucet, Garbage Disposal | 0.47% | $2,233 | $0.82 | |
Laundry Sink and Faucet | 0.23% | $1,110 | $0.41 | |
HVAC | 4.80% | $22,953 | $8.43 | |
Equipment Efficiency Premium (High AFUE and/or SEER) | 0.24% | $1,154 | $0.42 | |
Air Infiltration Premium (Very Tight Home Construction, Heat Exchanger) | 0.00% | $0 | $0.00 | |
Gas Forced Air Furnace, Air Conditioning, Metal Ductwork | 4.56% | $21,799 | $8.00 | |
Direct Vent Fireplace | 0.00% | $0 | $0.00 | |
ELECTRICAL | 2.83% | $13,549 | $4.97 | |
Electrical Service, Power Panel, Distribution | 1.61% | $7,687 | $2.82 | |
Fixed Lighting | 1.23% | $5,863 | $2.15 | |
Security System, Hard Wired Fire / Smoke Detection | 0.00% | $0 | $0.00 | |
APPLIANCES AND FIXTURES | 2.04% | $9,750 | $3.58 | |
Refrigerator/Freezer, Dishwasher, Stove, Exhaust Hood, Washer / Dryer | 1.38% | $6,622 | $2.43 | |
Closet Systems | 0.65% | $3,128 | $1.15 | |
Special Construction | 0.00% | $0 | $0.00 | |
PROJECT DEVELOPMENT | 12.28% | $58,746 | $21.57 | |
Contractor General Conditions, Site Supervision, Overhead and Profit | 12.28% | $58,746 | $21.57 |