Schematic Design Option 3.1
SD 3.1 – 360° Panorama
SD 3.1 – 3D MODEL
SD 3.1 OVERVIEW
Primary Style | Victorian |
Stories: | 1-1/2 |
Bedrooms: | 3 |
Baths: | 3 |
Garage Bays: | 2 |
Living Area: | 2,956 sq.ft. |
Foundation: | Basement |
Width: | 71′ |
Depth: | 56′ |
Styles: | Queen Anne Country Farmhouse |
SD 3.1 FEATURES
Basement Ceiling Height | 7′ – 8″ |
Main Level Ceiling Height | 9′ |
2nd Level Ceiling Height | 8′ |
Exterior Wall Types: | 2x6 |
Front Facade: | Siding/ Stone |
Rear Facade: | Siding |
Left Side Facade: | Siding |
Right Side Facade: | Siding |
Wraparound Porch | Yes |
Vaulted/Cathedral Ceilings | Yes |
Kitchen Island | Yes |
Storage/Attic Space | Yes |
FirePlace | Yes |
1st Floor Master Suite | Yes |
Breakfast Nook | Yes |
Built-In Cabinets, Shelves, Desks | Yes |
French Doors | Yes |
Bay/Box/Bow Windows | Yes |
SD 3.1 HOME DETAILS
Total Finished Area: | 2,956 sq. ft. |
Main Level Area: | 1,814 sq ft. |
2nd Level Area: | 1,142 sq ft. |
Storage Area: | 784 sq ft. |
Unfinished Basement Area: | 1,870 sq ft. |
Main Garage Area: | 783 sq ft. |
Shop Area: | 783 sq ft. |
Basement Garage Area: | 1,870 sq ft |
Deck Area: | 338 sq ft. |
Total Construction Area: | 7,514 sp ft. |
Max Ridge Height: | 23.75 Ft |
Primary Roof Pitch: Roof Framing: |
12:12 Pitch Truss/ Hand Framed |
SD 3.1 ROOM SCHEDULE
SD 3.1 INITIAL COST OF WORK ESTIMATES
QUALITY LEVEL: + ABOVE
COST RANGE: LOW
Percentage | Price | $/ Sq Ft | ||
TOTAL: | 100.00% | $492,529 | $166.62 | |
SITEWORK AND EXCAVATION | 2.72% | $13,380 | $4.53 | |
Site Clearing and Grading | 0.00% | $0 | $0.00 | |
Driveway, Walkway, Patio, Deck, Landscaping | 1.91% | $9,423 | $3.19 | |
Site Electrical, Gas, Water, Sewer Utility Extensions | 0.46% | $2,272 | $0.77 | |
Excavation (foundations) | 0.34% | $1,685 | $0.57 | |
FOUNDATIONS AND FOOTINGS | 9.99% | $49,204 | $16.65 | |
Home Foundation Walls | 0.67% | $3,303 | $1.12 | |
Home Footings | 0.38% | $1,850 | $0.63 | |
Deck Footings | 0.83% | $4,099 | $1.39 | |
Structural Concrete | 0.15% | $717 | $0.24 | |
Slabs (home, garage, basement, crawlspace) | 2.21% | $10,881 | $3.68 | |
Basement Excavation, Poured Concrete Walls/Footings, Drainage, Rigid Insulation | 5.76% | $28,355 | $9.59 | |
STRUCTURAL AND FRAMING | 21.83% | $107,515 | $36.37 | |
Home Floor Framing | 5.97% | $29,414 | $9.95 | |
Deck Floor Structure | 0.27% | $1,320 | $0.45 | |
Home Roof Structure | 5.35% | $26,345 | $8.91 | |
Deck Roof Structure | 1.06% | $5,228 | $1.77 | |
Garage Roof Structure and Shingles | 1.12% | $5,523 | $1.87 | |
Exterior Wall Framing, Insulation, Sheathing; House Wrap | 6.82% | $33,601 | $11.37 | |
Interior Partition Wall Framing | 1.24% | $6,084 | $2.06 | |
SIDING AND EXTERIOR TRIM | 6.21% | $30,593 | $10.35 | |
Exterior Wall Finish Material | 6.21% | $30,593 | $10.35 | |
Special Trim Complexity | 0.00% | $0 | $0.00 | |
EXTERIOR DOORS AND WINDOWS | 5.57% | $27,438 | $9.28 | |
Exterior Windows, Trim | 4.51% | $22,222 | $7.52 | |
Exterior Passage Doors, Doorwall, Overhead Garage Doors, Trim | 1.06% | $5,217 | $1.76 | |
ROOFING AND GUTTERS | 5.69% | $28,025 | $9.48 | |
Home Roofing Shingles | 2.20% | $10,846 | $3.67 | |
Porch Roofing Shingles | 0.22% | $1,071 | $0.36 | |
Roof Guttering | 0.62% | $3,031 | $1.03 | |
Special Roof Valley | 0.00% | $0 | $0.00 | |
Roofing Soffit and Fascia | 1.98% | $9,749 | $3.30 | |
Attic Insulation | 0.68% | $3,329 | $1.13 | |
CABINETRY AND COUNTERTOPS | 5.26% | $25,898 | $8.76 | |
Kitchen Cabinetry, Countertops, Flooring | 2.78% | $13,705 | $4.64 | |
Master Bathroom Cabinetry, Mirror, Countertops, Flooring | 1.50% | $7,369 | $2.49 | |
Full Bathroom Cabinetry, Mirror, Countertops, Flooring | 0.86% | $4,255 | $1.44 | |
Half Bath Cabinetry, Mirror, Countertops, Flooring | 0.12% | $569 | $0.19 | |
STAIRS AND RAILS | 1.60% | $7,892 | $2.67 | |
Stair Construction | 0.98% | $4,850 | $1.64 | |
Railing and Balusters | 0.62% | $3,042 | $1.03 | |
INTERIOR DOORS AND MILLWORK | 3.25% | $16,003 | $5.41 | |
Interior Doors, Hardware, Trim and Finishing | 2.41% | $11,875 | $4.02 | |
Baseboard Molding and Finishing | 0.84% | $4,128 | $1.40 | |
INTERIOR CEILING AND WALL COVERINGS | 6.87% | $33,820 | $11.44 | |
Interior Drywall: Walls | 1.73% | $8,518 | $2.88 | |
Interior Wall Primer and Painted Finish | 1.31% | $6,471 | $2.19 | |
Interior Drywall: Ceiling | 3.37% | $16,606 | $5.62 | |
Porch Ceiling Surfaces | 0.45% | $2,225 | $0.75 | |
INTERIOR CEILING AND WALL FINISHES | 4.15% | $20,433 | $6.91 | |
Interior Ceiling Primer and Painted Finish | 0.59% | $2,887 | $0.98 | |
Interior Floor Finishes | 3.56% | $17,546 | $5.94 | |
PLUMBING | 4.92% | $24,221 | $8.19 | |
Water Supply, Distribution, Waste, Water Heater | 1.74% | $8,574 | $2.90 | |
Bathroom Fixtures (Master Bath): Sink/Faucet, Toilet, Tub/Shower, Supply/Waste/Vent | 1.13% | $5,548 | $1.88 | |
Bathroom Fixtures (Full Bath): Sink, Faucet, Toilet, Tub/Shower, Supply, Waste, Vent | 0.77% | $3,785 | $1.28 | |
Bathroom Fixtures (Half Baths): Pedestal Sink, Faucet, Supply, Waste, Vent | 0.21% | $1,029 | $0.35 | |
Bathroom Fixtures (Half Baths): Toilet, Supply, Waste, Vent | 0.21% | $1,019 | $0.34 | |
Tub Enclosures | 0.17% | $824 | $0.28 | |
Kitchen Sink, Faucet, Garbage Disposal | 0.47% | $2,299 | $0.78 | |
Laundry Sink and Faucet | 0.23% | $1,143 | $0.39 | |
HVAC | 4.80% | $23,632 | $7.99 | |
Equipment Efficiency Premium (High AFUE and/or SEER) | 0.24% | $1,188 | $0.40 | |
Air Infiltration Premium (Very Tight Home Construction, Heat Exchanger) | 0.00% | $0 | $0.00 | |
Gas Forced Air Furnace, Air Conditioning, Metal Ductwork | 4.56% | $22,445 | $7.59 | |
Direct Vent Fireplace | 0.00% | $0 | $0.00 | |
ELECTRICAL | 2.83% | $13,950 | $4.72 | |
Electrical Service, Power Panel, Distribution | 1.61% | $7,914 | $2.68 | |
Fixed Lighting | 1.23% | $6,036 | $2.04 | |
Security System, Hard Wired Fire / Smoke Detection | 0.00% | $0 | $0.00 | |
APPLIANCES AND FIXTURES | 2.04% | $10,039 | $3.40 | |
Refrigerator/Freezer, Dishwasher, Stove, Exhaust Hood, Washer / Dryer | 1.38% | $6,818 | $2.31 | |
Closet Systems | 0.65% | $3,220 | $1.09 | |
Special Construction | 0.00% | $0 | $0.00 | |
PROJECT DEVELOPMENT | 12.28% | $60,486 | $20.46 | |
Contractor General Conditions, Site Supervision, Overhead and Profit | 12.28% | $60,486 | $20.46 |